What Are the FEOC Supply Chain Tracing Requirements Under OBBBA?

By , Sr. Director, Supply Chain Compliance, Empact Technologies|Published

Projects subject to the prohibited foreign entity (PFE) rules must identify the manufactured products and manufactured product components in a facility, determine which of those are treated as PFE-produced under the applicable guidance and calculate the material assistance cost ratio against the applicable beginning-of-construction threshold. Supplier screening alone is not enough.

The One Big Beautiful Bill Act (OBBBA) extended prohibited foreign entity restrictions to the Section 45Y clean electricity production credit and the Section 48E clean electricity investment credit for facilities and energy storage technologies that begin construction after December 31, 2025. These requirements are commonly referred to as Foreign Entity of Concern (FEOC) restrictions. Under OBBBA and Notice 2026-15, however, the operative statutory term is prohibited foreign entity. Throughout this article, I use the statutory terminology when discussing the requirements in Notice 2026-15. The Notice provides interim guidance on how taxpayers identify manufactured products and manufactured product components, determine direct costs, calculate the material assistance cost ratio (MACR) and apply the available safe harbors while Treasury and the IRS develop proposed regulations.

What Supply Chain Tracing Actually Means

Supply chain tracing answers a different question from entity screening. Entity screening determines whether the entity that mined, produced or manufactured a relevant manufactured product or manufactured product component was a prohibited foreign entity for the applicable taxable year. Tracing asks how much of the relevant direct cost of a qualified facility or energy storage technology is attributable to manufactured products or manufactured product components produced by a PFE.

A project can clear an entity-level review and still fail the material assistance test. A direct supplier that is not itself a PFE may incorporate components produced by a PFE. For that reason, a supplier certification can be an important input, but it does not replace the component-level analysis required to calculate MACR.

The Two Levels the Record Must Reach

The analysis depends on records that distinguish between the following levels:

Manufactured product: The finished product incorporated into the facility, such as a solar module, inverter, wind turbine component or battery enclosure.

Manufactured product component: A component incorporated into a manufactured product, such as cells, frames or glass. The tracing analysis must identify and track these components.

Structural steel or iron items are generally disregarded in the Clean Electricity MACR unless they are otherwise identified as manufactured products or manufactured product components under the applicable rules.

A summary bill of materials that stops at the finished-product level does not support the calculation. The compliance file must connect the project-level result to the underlying products, components, suppliers, costs and sourcing determinations used to produce it.

How the Material Assistance Cost Ratio Is Calculated

Under Notice 2026-15, a taxpayer calculating the Clean Electricity MACR generally must identify the manufactured products and manufactured product components included in the facility or energy storage technology, determine the relevant direct costs attributable to those products and components and determine which of those direct costs are attributable to products or components produced by a PFE.

For an acquired manufactured product, direct costs generally consist of the taxpayer's acquisition costs. If the taxpayer manufactures the product, direct costs generally include direct material and direct labor costs. Costs of incorporating the manufactured product into the facility or energy storage technology are not included in the direct costs attributable to that product.

The ratio measures the share of total relevant direct costs that are not attributable to PFE-produced products or components. The calculation subtracts aggregate PFE direct costs from total direct costs and divides the result by total direct costs. If the resulting MACR is below the applicable statutory threshold, the facility or energy storage technology includes material assistance from a PFE and is not eligible for the applicable credit.

The calculation must be supported, not merely stated. A final percentage without the component identification, cost records, supplier information, sourcing determinations and methodology behind it will not constitute a complete substantiation record.

The Thresholds and When They Apply

For qualified facilities and energy storage technologies, the threshold is based on the calendar year in which construction begins:

Beginning-of-construction yearQualified facilityEnergy storage technology
202640%55%
202745%60%
202850%65%
202955%70%
After 202960%75%

Because the applicable percentage turns on the year construction begins, the project's beginning-of-construction analysis and supporting records directly affect the material assistance result. The material assistance restrictions apply to Section 45Y facilities for which construction begins after December 31, 2025, and to Section 48E qualified facilities or energy storage technologies for which construction, reconstruction or erection begins after that date.

45X Eligible Component MACR Thresholds

Developers and manufacturers often sit on opposite sides of the same supply chain. A manufacturer claiming Section 45X on a component it produces runs its own material assistance analysis on that component, separate from the project-level analysis run by the developer that buys it. Both analyses draw on the same underlying sourcing and cost records.

The Section 45X advanced manufacturing production credit uses a separate Eligible Component MACR threshold schedule based on the calendar year in which the eligible component is sold, rather than the project's beginning-of-construction year:

45X eligible componentSale yearThreshold
Solar energy component202650%
Solar energy component202760%
Solar energy component202870%
Solar energy component202980%
Solar energy componentAfter 202985%
Wind energy component202685%
Wind energy component202790%
Inverter202650%
Inverter202755%
Inverter202860%
Inverter202965%
InverterAfter 202970%
Qualifying battery component202660%
Qualifying battery component202765%
Qualifying battery component202870%
Qualifying battery component202980%
Qualifying battery componentAfter 202985%
Applicable critical mineral2026–20290%
Applicable critical mineral203025%
Applicable critical mineral203130%
Applicable critical mineral203240%
Applicable critical mineralAfter 203250%

The Section 45X credit terminates for wind energy components sold after December 31, 2027. No threshold applies for later sale years.

Note: The applicable critical mineral thresholds shown above reflect the statutory schedule in Section 7701(a)(52)(C). OBBBA directs Treasury to issue adjusted threshold percentages for individual applicable critical minerals by December 31, 2027.

Wind energy components are not listed after 2027 because Section 45X does not apply to wind energy components produced and sold after December 31, 2027.

Safe Harbors Reduce the Calculation Burden, Not the Documentation Obligation

Notice 2026-15 provides interim identification, cost-percentage and certification safe harbors. Depending on the safe harbor used, a taxpayer may rely on assigned component classifications or assigned cost percentages found in Notice 2025-08 rather than determining every relevant cost using actual direct-cost records.

Reliance is conditional. A taxpayer using a safe harbor must apply the applicable safe-harbor requirements and methodology consistently, retain substantiation under Section 6001 and attach a statement identifying the safe harbor and how it was applied to the relevant credit form for the first taxable year in which the credit is claimed.

The practical point is that a safe harbor can simplify the calculation, but it does not eliminate the documentation required to support it. The project still needs records showing which products and components were included, which were treated as PFE-produced, which safe harbor was used and how the final MACR was derived.

What This Changes Operationally

Material assistance compliance must begin during procurement, ideally while suppliers are being vetted and material supply agreements negotiated, not after construction is complete. Developers and manufacturers need a repeatable process to:

  • collect bills of materials and component-level supplier data before contracting;
  • screen direct suppliers and relevant upstream producers for PFE status;
  • capture the cost and sourcing information needed for the selected MACR methodology;
  • document the beginning-of-construction year and applicable threshold;
  • retain certifications, calculations, underlying records and methodology in a retrievable compliance file; and
  • update the analysis when products, suppliers or sourcing relationships change.

This is where the gap between legal interpretation and operational execution becomes material. The statute and guidance establish the test. The project team must build and maintain the evidence that shows how the test was applied.

Frequently Asked Questions

Does a signed supplier certification satisfy the material assistance requirement?

Not by itself. Notice 2026-15 permits reliance on a supplier certification when the Certification Safe Harbor's specific content, execution, retention and reliance requirements are satisfied. A general supplier representation or self-certification is not the Certification Safe Harbor. Even when a qualifying certification is used, the taxpayer must calculate the applicable MACR, retain the required substantiation and satisfy the Notice's reporting requirements.

Is MACR calculated for the entire project or separately for each product?

For Sections 45Y and 48E, Notice 2026-15 describes a Clean Electricity MACR for the qualified facility or energy storage technology. The project-level ratio is built from the manufactured products and manufactured product components included in that facility or technology, together with the relevant direct costs and PFE direct costs. The underlying analysis therefore remains component-level even though the eligibility determination applies to the qualified facility or energy storage technology.

Which year's MACR threshold applies to a project?

For Sections 45Y and 48E, the applicable threshold is set by the calendar year in which construction begins. For Section 45X eligible components, the applicable threshold is set by the calendar year in which the component is sold.

What records should a project retain?

A defensible file should include the component-level bill of materials, identification of relevant suppliers and producers, cost information used in the calculation, sourcing and PFE determinations, supplier certifications, the selected safe harbor or cost methodology, the MACR calculation and a written explanation of how the methodology was applied. Records must remain available for as long as they may be material to the administration of the tax law.

Empact Technologies protects tax credit eligibility with compliance records that stay complete, traceable and defensible throughout the life of the credit. NexusIQ™ operationalizes FEOC supply chain tracing and maintains component-level, audit-ready documentation for developers and manufacturers.

Contact Empact

This article reflects Empact Technologies' interpretation of the prohibited foreign entity supply chain requirements under OBBBA and Notice 2026-15 as of publication. It is not legal advice. Developers, manufacturers and suppliers should consult tax counsel regarding the application of these rules to their specific facts.

Filed Under

FEOC ComplianceSupply Chain TracingMaterial AssistanceClean Energy Tax Credits

Build a material assistance record that holds up.

Talk to Empact about component-level FEOC supply chain tracing through NexusIQ™, from bills of materials and PFE screening to MACR calculations and safe harbor documentation.